In an update to previous information, we have received confirmation that the tower crane from the Hale Works site, delivered by Wates will be removed this coming weekend with an east bound lane closure from the junction of Broad Lane through to Mill mead road. The process will start from this Friday 2 April at 10pm and run through to 5am on Monday 5 April when the eastbound lane on Ferry lane will be completely re-opened to all traffic.
It is important to note however that the removal of the crane is weather dependable, and wind or rain may cause further delay.
Please accept our apologies for any inconvenience caused.